Here are some progress pictures of the Mudroom Powder Room, the front and side entry doors installed, window seat framing, master bath shower, bonus room...
While the Tate's are in FL for a week in the sun, beachin it...the house will still be speeding along. Plans for week of 6/23 include, but are not necessarily limited to: completion of plumbing and electrical rough ins, inspection by Township of these rough ins, upon approval insulation of walls and ceilings, and installation of drywall by the end of the week. We are reviewing the final lighting fixture selections which Jennifer has worked so diligently to pull together. We will be making the final selections on the wood trim throughout the house.